Council Targets and the New DA League Table Explained
By Adam Murphy, Principal Building Designer — ANS Design
Information current as at 19th September 2026
In 2026, that question has become particularly relevant because the NSW Government is placing increasing emphasis on development assessment times and publicly reporting council performance through the NSW Council League Table.
From 1 July 2026, the NSW Government’s updated Statement of Expectations Order 2026 sets an expectation that councils determine Development Applications within an average of 90 days from lodgement, or within the council’s previous financial-year average where that figure is lower.
However, this does not mean that every DA in NSW must be approved or refused within 90 days.
The 90-day figure is a council performance measure, rather than a guaranteed determination period for an individual application.
That distinction is important for homeowners, developers and consultants trying to realistically plan a project.
What is the 90-day DA target in NSW?
The current benchmark comes from the Statement of Expectations Order 2026, which commenced on 1 July 2026.
Under the current framework, councils are expected to determine DAs for which they are the consent authority as soon as practical and within the lesser of their previous financial-year average or the following average assessment periods:
| Financial year | Council determination expectation |
|---|---|
| 1 July 2026 – 30 June 2027 | 90 days average |
| 1 July 2027 – 30 June 2028 | 80 days average |
| From 1 July 2028 | 65 days average |
These are progressively reducing performance expectations intended to improve development-assessment efficiency across NSW.
You can read the current requirements through the NSW Government Statement of Expectations Order page.
This is also why some earlier information refers to 95 days for 2026–27. That figure related to the previous framework. The updated 2026 Order now sets the current expectation at 90 days from 1 July 2026.
Does this mean Council has to determine my DA within 90 days?
No.
This is probably the most important point for applicants to understand.
The 90-day expectation is an average performance benchmark applying across a council’s DA assessment workload. It is not a promise that every individual application will receive a determination within 90 calendar days.
The NSW Department of Planning, Housing and Infrastructure acknowledges that Development Applications vary substantially in their type, scale, planning merit and the quality of documentation provided. This is one reason the expectation is measured as a council-wide average rather than imposing the same period on every application.
A straightforward alterations and additions application with comprehensive documentation and relatively few planning issues may potentially be determined considerably faster.
A more complicated application involving development-standard variations, heritage considerations, flooding, bushfire constraints, biodiversity, significant submissions, external referrals or substantial Requests for Information may take considerably longer.
NSW Government homeowner guidance states that most councils determine straightforward and complete applications in 40 days or less.
For more information, see the NSW Government guide to lodging a Development Application.
So the question should not simply be:
“Is the target 90 days?”
A more useful question is:
“How complex is this particular DA, how complete is the application, and how is the relevant council currently performing?”
What is the NSW Council League Table?
The NSW Government’s Council League Table publicly reports development assessment performance using information obtained through the NSW Planning Portal.
The league table monitors both the time councils take to move applications from submission to lodgement and the time taken to move a DA from lodgement to determination.
Council performance has been captured monthly since 1 July 2024, with performance captured on the sixth business day of each month.
Applicants and property owners can therefore look at published data showing how a particular council is performing rather than relying entirely on general estimates.
You can view the current figures through the NSW Council League Table and interactive dashboard.
The league table can be particularly useful during project feasibility and programming because it provides an indication of the current development-assessment environment within a local government area.
It should not, however, be treated as a forecast of exactly how long your particular application will take
What are councils currently recording?
The differences between councils can be significant.
The NSW Government’s August 2026 snapshot, published as at 8 September 2026, included the following figures for councils relevant to many ANS Design projects:
| Council | Average lodgement days | Average assessment days |
|---|---|---|
| Ryde | 8 | 87 |
| Parramatta | 12 | 92 |
| Penrith | 4 | 107 |
| Blacktown | 5 | 112 |
| Northern Beaches | 4 | 81 |
| Newcastle | 6 | 80 |
| Hawkesbury | 7 | 82 |
| Inner West | 3 | 94 |
| Central Coast | 6 | 112 |
| The Hills | 7 | 95 |
| Willoughby | 17 | 70 |
These are the published August 2026 snapshot figures and can change as further DAs are determined.
The complete and most current results should therefore always be checked through the NSW Council League Table before relying on a particular figure.
These figures demonstrate why it is difficult to give a universal answer to the question of how long a DA “should” take.
They are also averages across determined applications.
They do not mean that every Penrith DA will take 107 days, that every Blacktown DA will take 112 days, or that every Willoughby application will be completed within 70 days.
Individual applications can be substantially quicker or substantially longer.
Submission and lodgement are not the same thing
Another issue that can cause confusion is the difference between submitting a Development Application through the NSW Planning Portal and the application actually being lodged.
Uploading and submitting an application does not necessarily mean the formal assessment period has immediately commenced.
The 2026 Statement of Expectations says councils should progress Development Applications from submission to lodgement within an average of seven days.
It also sets expectations that councils undertake an adequacy review within four days of submission and issue an invoice within four days, with the applicant then given three business days to make payment.
The application process can therefore broadly be viewed as:
Submission → Lodgement → Assessment → Determination
Applicants can lodge and track applications using the NSW Planning Portal.
A well-prepared application can help make the submission and lodgement stage more straightforward.
How does the League Table calculate assessment time?
There is another important feature of the current reporting system.
Council assessment performance is measured using gross days.
That means the calculation counts the total number of calendar days between lodgement and determination, including weekends and public holidays.
Importantly, the league-table calculation does not remove “stop the clock” periods when council is waiting for additional information from an applicant.
This makes the figure particularly relevant from the applicant’s perspective.
If an application sits for several weeks while revised architectural drawings, engineering information or other material is being prepared, those weeks are still part of the real-world time experienced between lodgement and determination.
The Department considers these end-to-end timeframes a more meaningful measure for the community and industry.
Further information about the methodology is available through the Statement of Expectations and Council League Table guidance.
What happens when Council requests additional information?
A Request for Information, commonly referred to as an RFI, can be one of the largest contributors to an extended DA timeframe.
Council may identify matters during assessment that require clarification or further documentation.
These could relate to architectural amendments, planning justification, stormwater, structural engineering, landscaping, arboricultural matters, flooding, bushfire, contamination, acoustics, privacy, overshadowing, access or proposed variations to planning controls.
The more significant the issue, the greater the potential impact on the project program.
This is why good development documentation is not simply about producing enough information to lodge an application.
Where possible, planning issues should be identified before lodgement.
ANS Design has prepared a separate article explaining how early review of LEPs, DCPs, SEPPs, Section 10.7 Planning Certificates, mapping, surveys and site constraints can help identify potential issues before a DA or CDC is prepared.
Read: NSW Planning Due Diligence – Why It Matters Before a DA or CDC
Early planning research cannot guarantee approval, but it can help identify unsuitable development options, likely consultant requirements and potential compliance issues before substantial design work is undertaken.
External agency referrals can also affect the timeframe
Some developments require input from NSW Government agencies or other authorities.
From 1 July 2026, the NSW Government introduced the Development Coordination Authority (DCA) to coordinate government input into planning matters.
The DCA brings together government expertise that was previously distributed among numerous parts of government and provides a coordinated pathway for referrals.
Learn more about the NSW Development Coordination Authority
For local DAs lodged under the current framework, the DCA and other organisations generally have 28 calendar days to respond to a referral.
The 28-day period starts once the referral is made through the Planning Portal and required fees are paid. The clock pauses if further information is requested and restarts when that information is provided.
View DCA referral timeframes and fees
The NSW Government also publishes an Agency League Table showing the performance of agencies responding to referrals.
The Agency League Table records the number of referrals completed and the percentage completed within the legislated timeframe.
What happens if councils continually miss the expectations?
The council league table is not simply a public reporting tool.
For 2026–27, the Department identifies councils that may require additional attention using criteria including councils taking 90 days or more on average to determine DAs and councils where 60% or less of applications meet the expected timeframe. Housing targets and projected dwelling demand are also considered.
Councils not meeting expectations may be asked to explain the reasons for their performance and identify improvement opportunities.
The Department may work with a council on an action plan or provide additional planning resources and support.
If performance does not improve, the current framework provides for further measures that may include consideration of a Performance Improvement Order or, in some circumstances, a planning administrator.
The full process is explained in the NSW Statement of Expectations guidance.
Again, these mechanisms relate to council-wide performance.
They do not create a personal guarantee that an individual homeowner’s DA will be determined within 90 days.
What about the 40-day “deemed refusal” period?
This is another area where terminology can easily become confusing.
The planning system also contains deemed-refusal assessment periods, which can provide an applicant with appeal rights where an application remains undetermined.
These statutory periods are separate from the NSW Government’s council-performance targets.
The NSW Government’s 2026 planning reform guidance confirms that deemed-refusal assessment periods vary from 40 to 90 days after lodgement depending on the development type, excluding applicable stop-the-clock periods.
Read the NSW Government planning reform guidance on deemed refusals and appeal periods
A deemed refusal does not necessarily mean council physically issues a refusal notice on that date.
Nor does the expiry of a deemed-refusal period mean that an application automatically becomes approved.
It is therefore important not to confuse:
a statutory deemed-refusal or appeal period
with
the 90-day council performance expectation.
They serve different purposes.
Why do some DAs take much longer than others?
In practice, the time required to determine a Development Application is influenced by considerably more than the name of the council.
A comparatively straightforward proposal that closely complies with the applicable Local Environmental Plan, Development Control Plan and relevant State Environmental Planning Policies may require relatively limited assessment.
By contrast, a proposal involving significant non-compliances or site constraints can require substantially more planning analysis.
Matters such as building height, floor space ratio, setbacks, landscaped area, privacy, overshadowing, streetscape, heritage, flooding, bushfire, biodiversity, traffic, vehicle access, stormwater disposal and tree impacts can all affect the assessment.
Public notification and submissions may also raise issues that require further consideration or design responses.
The quality and coordination of the original DA package can therefore make a substantial difference.
Can a well-prepared DA be assessed faster?
There is never a guarantee because the determination remains with the relevant consent authority.
However, reducing avoidable planning and documentation problems before lodgement can reduce the likelihood of unnecessary delays later.
A strong DA package should clearly explain the proposed development, identify the relevant planning controls, demonstrate where the proposal complies and appropriately address areas where it does not.
Architectural drawings, the Statement of Environmental Effects and supporting consultant documentation should also be coordinated.
If architectural drawings indicate one outcome while the Statement of Environmental Effects describes another, or engineering documentation conflicts with architectural plans, council may need additional clarification.
Early feasibility work can therefore be valuable.
ANS Design provides assistance with Development Application documentation, Statements of Environmental Effects, planning reviews, consultant coordination and council submission support.
View ANS Design’s Building Design, DA and CDC Services
The DA timeframe should start before the DA is lodged
For owners considering alterations and additions, a new dwelling, secondary dwelling, duplex or another residential development, one of the most effective approaches is to investigate the planning pathway early.
Before detailed documentation is completed, it can be useful to establish the property’s zoning, applicable development standards, site constraints, approval pathways and likely areas of non-compliance.
This can identify whether a proposal could potentially qualify for Complying Development, whether a conventional Development Application is required, and what specialist reports or consultant documentation may be needed.
It can also identify design decisions that may unnecessarily complicate a future approval.
ANS Design’s approval process explains how early planning, concept design, DA or CDC documentation and consultant coordination can be incorporated into the project from the beginning.
View the ANS Design Approvals & Design Process
The objective is not simply to lodge an application quickly.
It is to lodge an application that is well considered and capable of progressing efficiently through assessment.
So, how long should you allow for a DA in NSW in 2026?
There is no single number that applies to every project.
For a straightforward and complete proposal, determination may occur considerably faster than 90 days. NSW Government homeowner guidance says most councils determine straightforward and complete applications within 40 days or less.
For broader council performance, however, the current 2026–27 Statement of Expectations benchmark is an average of 90 days from lodgement, or the council’s previous financial-year average where that figure is lower.
More complex applications may take considerably longer.
The most useful way to consider the likely timeframe is therefore to look at three factors together:
the complexity of the proposal, the quality and completeness of the DA documentation, and the current performance of the relevant council.
The NSW Council League Table now gives homeowners, consultants and developers much greater visibility of that final factor.
Final Thoughts
The publication of council assessment data is changing the amount of information available to people planning development in NSW.
Instead of relying solely on general estimates, homeowners, designers and developers can review current council-performance information and consider it alongside the complexity of their particular proposal.
But the figures need to be interpreted correctly.
The 90-day figure is an average council performance expectation — it is not a guaranteed approval timeframe for an individual Development Application.
A DA that is carefully designed, properly researched and comprehensively documented is still better placed to move through the assessment process without avoidable delays.
For anyone considering a residential project in NSW, early planning and feasibility work can help identify the appropriate approval pathway, applicable planning controls and potential issues before substantial time and money are committed to detailed documentation.
Planning a Residential Project in NSW?
ANS Design provides residential building design, planning and development assistance, including preliminary feasibility assessments, planning-control reviews, DA and CDC pathway advice, Development Application documentation, Statements of Environmental Effects, consultant coordination and council submission support.
ANS Design works across Sydney, Greater Sydney, the Hills District and North-West, Parramatta, the Inner West, Penrith and Greater Western Sydney, Blacktown and Western Sydney, Hawkesbury, Northern Beaches and Northern Sydney, the Central Coast, Lake Macquarie, Newcastle, the Hunter Region and selected regional NSW locations.
Learn About Adam Murphy and ANS Design
Contact Adam Murphy at ANS Design
This article provides general information only and should not be relied upon as legal or project-specific planning advice. Planning legislation, policies, council procedures and assessment data can change. The requirements applying to an individual property and proposal should always be confirmed at the time the project is being considered.